At this stage, your current focus is a final update of the remaining open key dates and deliverables to ensure that they remain aligned to the closed project schedule. It is important that any changes in status are communicated to the project stakeholders effectively.

To complete key dates and deliverables:

1. Complete deliverables

  1. Open the Key Dates tab for the project.

  2. For all Key Dates that are not Done:


    ٠ If the dates match, drag and drop the Key Date card to the Done column.


    ٠ If the dates do not match, select the pencil icon (or double click the Key Date card). 

  3. Update the Date to reflect the current schedule.

  4. Set the Status to Done.

2.  Complete deliverables

  1. Open the Deliverables tab for the project.

  2. For all Deliverables that are not Completed select the Deliverable row.

  3. Click Edit (or double click the Deliverable name).

  4. Update the Due Date to reflect the current schedule.

  5. Set the Status to Completed.

Download Job Aid: Closing a project